The Brush Creek culvert replacement project has begun. Periodic weekly updates will be provided throughout the project. Project information can be found online at tosv.com/566/Brush-Creek-Culvert-Reconstruction
Comments, feedback, or suggestions for improvement can be shared with project@tosv.com. We appreciate your patience during this construction project!
Closures:
- Brush Creek Road remains closed for the duration of the project.
- The walking/bike trail along Brush Creek in the Blue Roofs area is open.
What Work Was Completed This Week?
- The concrete trail under the structure was completed.
- The downhill side of the structure has been backfilled almost to the finish grade.
Work Planned for the Update Period:
- Crews will be completing the waterproofing on the top of the culvert structure and starting to backfill on the uphill side.
Upcoming Traffic Flow Changes:
- None anticipated until the project is complete.